A Manager Wants to Analyze the Learning Curve Associated with Producing

Question 26

Multiple Choice

A manager wants to analyze the learning curve associated with producing one of his company's products. Accordingly, he has gathered the following data:  UNIT PRODUCED  TIME REQUIRED  Second 5 hours  Fourth 4 hours \begin{array} { | l | l | } \hline \text { UNIT PRODUCED } &{ \text { TIME REQUIRED } } \\\hline \text { Second } & 5 \text { hours } \\\hline \text { Fourth } & 4 \text { hours } \\\hline\end{array} Approximately how long will it take to produce the fifth through tenth units?


A) 15 hours
B) 16 hours
C) 18 hours
D) 20 hours