Solved

The Third Unit of a 10-Unit Job Required 7

Question 41

Essay

The third unit of a 10-unit job required 7.3 hours to complete. The fourth unit has been worked on for two hours, but it is not yet finished. Estimate the remaining amount of time that will be needed to finish this 10-unit job if the work has an 80 percent learning curve.

Correct Answer:

verifed

Verified

We will need 37.66 h...