Multiple Choice
QRS Corp. is designing a product layout for a new product. They plan to use this production line 10 hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product: Without considering forecasted demand, what is the minimum possible cycle time for this production line?
A) 10 seconds
B) 20 seconds
C) 34 seconds
D) 38 seconds
E) 152 seconds