Multiple Choice
A company needs to locate three departments (X, Y, and Z) in the three areas (I, II, and III) of a new facility. They want to minimize interdepartmental transportation costs, which are expected to be $.50 per load meter moved. An analyst has prepared the following flow and distance matrices: What is the layout that will minimize the total distance loads will be moved each week?
A) X in 1; Y in 2; Z in 3
B) X in 1; Z in 2; Y in 3
C) Y in 1; X in 2; Z in 3
D) Z in 1; X in 2; Y in 3
E) Z in 1; Y in 2; X in 3
Correct Answer:

Verified
Correct Answer:
Verified
Q16: An operations strategy for process selection should
Q29: Job shops tend to be _ while
Q31: A company needs to locate three
Q32: A production line is to be designed
Q36: Given the following process layout data
Q37: Computer-integrated manufacturing integrates _ with manufacturing.<br>A) information
Q38: QRS Corp. is designing a product
Q56: Computer-aided manufacturing refers to the use of
Q86: In the use of closeness ratings for
Q89: Product profiling links key product or service