A time study was made of a job to develop new time standards.A worker was observed for 30 minutes.During that time,40 units were produced.The analyst rated the worker as performing at a 120 percent performance rate.What is the normal time for this task?


A) 0.80 minutes
B) 0.90 minutes
C) 1.00 minutes
D) 1.20 minutes
E) 1.33 minutes

Correct Answer: