Multiple Choice
A simple project listing of five activities and their respective time estimates are presented below:
Using the Single Time Estimate CPM procedure,which activities make up the critical path?
A) A,C,D,E
B) A,B,D,E
C) A,C,B,D,E
D) A,D,E
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q1: Derivative projects are those which address incremental
Q5: The critical path in a project is
Q69: Using the Time-Cost CPM model, the crash
Q71: You have collected the data for
Q72: If you have an optimistic time of
Q74: A listing of immediate predecessor activities is
Q75: If the pessimistic duration of an activity
Q78: You have just computed a Z=2.55 in
Q79: If each activity time is known with
Q104: In CPM, the late start time estimate