Multiple Choice
You have just computed a Z=2.55 in a CPM analysis of a critical path for a project.Based on this Z value what is the probability of completing this project on time?
A) 0.76543
B) 0.67543
C) 0.99061
D) 0.99461
E) You cannot tell based on the information given
Correct Answer:

Verified
Correct Answer:
Verified