Multiple Choice
A simple project listing of five activities,their predecessors and their respective time estimates are presented below:
Using the Single Time Estimate CPM procedure,what is the Latest Finish Time for the last activity in this project (i.e. ,the total time to complete the project) ?
A) 10 days
B) 7 days
C) 8 days
D) 12 days
E) 9 days
Correct Answer:

Verified
Correct Answer:
Verified
Q2: Most project work is controlled by PERT
Q3: Below are the data for a Time-Cost
Q7: You have collected the data for
Q10: You have determined the critical path in
Q11: The expected time estimate in a CPM
Q39: When reducing the planned duration of a
Q53: You know when you have arrived at
Q72: What is the criterion for determining whether
Q79: Slack activity time is the difference between
Q105: Breakthrough projects are those that provide fundamental