Question 4

Multiple Choice

A simple project listing of five activities,their predecessors and their respective time estimates are presented below:  Activity  Immediate Predecessor  Time in Days  A  None 3 B  A 2 C  A 1 D  B and C 3 E  D 4\begin{array}{|l|l|l|}\hline \text { Activity } & \text { Immediate Predecessor } & \text { Time in Days } \\\hline \text { A } & \text { None } & 3 \\\hline \text { B } & \text { A } & 2 \\\hline \text { C } & \text { A } & 1 \\\hline \text { D } & \text { B and C } & 3 \\\hline \text { E } & \text { D } & 4 \\\hline\end{array}
Using the Single Time Estimate CPM procedure,what is the Latest Finish Time for the last activity in this project (i.e. ,the total time to complete the project) ?


A) 10 days
B) 7 days
C) 8 days
D) 12 days
E) 9 days