Multiple Choice
You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project "direct costs" are given below.
The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200 and 13 days they will be $100.If you crash this project by one day what is the total (i.e. ,direct and indirect) project cost?
A) $2,150
B) $2,300
C) $2,400
D) $2,450
E) $2,500
Correct Answer:

Verified
Correct Answer:
Verified
Q2: Most project work is controlled by PERT
Q3: Below are the data for a Time-Cost
Q4: A simple project listing of five
Q10: You have determined the critical path in
Q11: The expected time estimate in a CPM
Q12: You are working on a project that
Q39: When reducing the planned duration of a
Q72: What is the criterion for determining whether
Q79: Slack activity time is the difference between
Q105: Breakthrough projects are those that provide fundamental