Solved

You Have Collected the Data for a Time-Cost CPM Scheduling

Question 7

Multiple Choice

You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project "direct costs" are given below.  Immediate  Normal  Crash  Normal  Crash  Activity  Predecessor  Time  Time  Cost (Direct)   Cost (Direct)   A  None 32$300$400 B  A 33$100$100 C  A 11$200$200 D  B and C 32$400$550 E  D 21$500$900 F  E 33$200$200 G  F 22$100$100\begin{array}{|l|l|l|l|l|l|}\hline & \text { Immediate } & \text { Normal } & \text { Crash } & \text { Normal } & \text { Crash } \\\hline \text { Activity } & \text { Predecessor } & \text { Time } & \text { Time } & \text { Cost (Direct) } & \text { Cost (Direct) } \\\hline \text { A } & \text { None } & 3 & 2 & \$ 300 & \$ 400 \\\hline \text { B } & \text { A } & 3 & 3 & \$ 100 & \$ 100 \\\hline \text { C } & \text { A } & 1 & 1 & \$ 200 & \$ 200 \\\hline \text { D } & \text { B and C } & 3 & 2 & \$ 400 & \$ 550 \\\hline \text { E } & \text { D } & 2 & 1 & \$ 500 & \$ 900 \\\hline \text { F } & \text { E } & 3 & 3 & \$ 200 & \$ 200 \\\hline \text { G } & \text { F } & 2 & 2 & \$ 100 & \$ 100 \\\hline\end{array}
The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200 and 13 days they will be $100.If you crash this project by one day what is the total (i.e. ,direct and indirect) project cost?


A) $2,150
B) $2,300
C) $2,400
D) $2,450
E) $2,500

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions