Multiple Choice
You are working on a project that has 12 activities and want to perform a CPM analysis on the project.You determine the critical path consists of only five activities.You then compute the variances for the five critical path activities and these variances are 3,4,2,1 and 6 days.If the desired completion date for the project is 50 days and the expected completion date for the project is 40 days,what is the probability that the project will be completed by the desired completion date?
A) 0.99379
B) 0.99180
C) 0.99772
D) 0.91924
E) 0.67364
Correct Answer:

Verified
Correct Answer:
Verified
Q7: You have collected the data for
Q10: You have determined the critical path in
Q11: The expected time estimate in a CPM
Q14: PERT is an abbreviation for which of
Q17: When the time estimates in a CPM
Q57: One of the assumptions made using CPM
Q72: What is the criterion for determining whether
Q76: A project milestone is a specific event
Q79: Slack activity time is the difference between
Q99: An advantage of a pure project where