    The Sum of Durations of the Longest Path in a Project
Solved

The Sum of Durations of the Longest Path in a Project

Question 57

Question 57

True/False

The sum of durations of the longest path in a project network indicates expected project completion time,and the activities are the critical activities

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q37: What is the estimated slack time for

Q53: PERT/Cost:<br>A)finds the penalty costs if a project

Q54: <br>-What is the estimated standard deviation

Q55: Projects involve routine activities that are performed

Q56: A Gantt chart of a project shows

Q58: PERT/Cost is a systematic procedure to help

Q59: The slack for path A-D-H-I is:<br>A)0 <br>B)3

Q60: A manager has decided that an activity

Q61: An immediate predecessor of an activity must

Q62: If an activity is not on the

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines