    In PERT,the Project Duration Will Never Exceed the Expected Duration
Solved

In PERT,the Project Duration Will Never Exceed the Expected Duration

Question 84

Question 84

True/False

In PERT,the project duration will never exceed the expected duration of the critical path

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q80: When making a backward pass through a

Q81: The latest finish of an activity is

Q81: What is the estimated slack time for

Q82: The earliest start of an activity is

Q83: <br>-What is the estimated mean time

Q85: <br>-What is the estimated mean time

Q86: The path with the greatest slack is:<br>A)A-E

Q87: The critical path is:<br>A)A-E <br>B)B-F <br>C)C-D-F <br>D)C-G

Q88: The length of the critical path is

Q89: The mean critical path is the path

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines