menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Introduction to Management Science
  4. Exam
    Exam 16: Pert CPM models for project management
  5. Question
    The Earliest Finish Time for an Activity Is Equal to the Latest
Solved

The Earliest Finish Time for an Activity Is Equal to the Latest

Question 43

Question 43

True/False

The earliest finish time for an activity is equal to the latest finish time minus the duration of the activity

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q20: Although PERT and CPM were originally developed

Q38: PERT/CPM can answer which of the following

Q39: Crashing cannot be accomplished by using different

Q40: The activities with the longest durations in

Q42: An activity in a project network cannot

Q44: There is currently no method that permits

Q45: The duration of the critical path is:<br>A)11

Q46: At which point does crashing of a

Q47: The critical path for the network shown

Q48: There are four activities on the critical

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines