True/False
A normal distribution is usually used to describe the form of the probability distribution of activity durations in the PERT three-estimate approach
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q82: The earliest start of an activity is
Q83: <br>-What is the estimated mean time
Q84: In PERT,the project duration will never exceed
Q85: <br>-What is the estimated mean time
Q86: The path with the greatest slack is:<br>A)A-E
Q87: The critical path is:<br>A)A-E <br>B)B-F <br>C)C-D-F <br>D)C-G
Q88: The length of the critical path is
Q89: The mean critical path is the path
Q90: The earliest start time for an activity
Q91: <br>-What is the estimated mean time