Solved

When Finding the Approximate Probability of Project Duration,it Is Necessary

Question 5

Multiple Choice

When finding the approximate probability of project duration,it is necessary to know which of the following?


A) The mean and variance of each activity
B) The mean of each activity on the critical path
C) The standard deviation of only the activities on the critical path
D) Each activity's probability of completion
E) The distribution of activity times

Correct Answer:

verifed

Verified