Multiple Choice
-What is the estimated mean time for activity Y?
A) 30 days
B) 29 days
C) 38 days
D) 26 days
E) 35 days
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q20: In a project network the critical path
Q21: Which of the following are ways of
Q22: The latest starting time for an activity
Q23: Activity C in a project network has
Q24: The path with the greatest slack is:<br>A)A-E-H
Q27: The standard deviation of the critical path
Q28: 51 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2459/.jpg" alt="51 A)22
Q29: Crashing an activity will always reduce the
Q30: Activities that are not on the critical
Q92: The expected duration of this project is:<br>A)13<br>B)15<br>C)20<br>D)52<br>E)81