Multiple Choice
When using linear programming to make crashing decisions,the objective is to minimize:
A) the total cost of crashing the project.
B) the total of the durations of the activities on the critical path.
C) the latest finish time of the finish node.
D) the total number of activities on the critical path.
E) None of the above.