Multiple Choice
The gross requirements of a part in an MRP system are determined from:
A) Net requirements + on-hand
B) Net requirements of end item
C) Gross requirements of the immediate part
D) Planned order releases of the immediate parent item
Correct Answer:

Verified
Correct Answer:
Verified