Multiple Choice
____ involves developing an approximation or estimate of the costs of the resources needed to complete a project.
A) Determining the budget
B) Consolidation of costs
C) Controlling costs
D) Estimating costs
Correct Answer:

Verified
Correct Answer:
Verified