Multiple Choice
____ are costs that are not directly related to the products or services of the project,but are indirectly related to performing the project.
A) Intangible costs
B) Tangible costs
C) Direct costs
D) Indirect costs
Correct Answer:

Verified
Correct Answer:
Verified