Multiple Choice
A(n) ____ might provide an estimate of $50 per line of code for a software development project based on the programming language the project is using,the level of expertise of the programmers,the size and complexity of the data involved,and so on.
A) analogous cost estimate
B) parametric model
C) bottom-up estimate
D) reserve analysis
Correct Answer:

Verified
Correct Answer:
Verified