    ____ Is a Project Performance Measurement Technique That Integrates Scope,time,and
Solved

____ Is a Project Performance Measurement Technique That Integrates Scope,time,and

Question 59

Question 59

Multiple Choice

____ is a project performance measurement technique that integrates scope,time,and cost data.


A) Cost baseline
B) Earned value management
C) Constructive cost modeling
D) Parametric modeling

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q54: What are tangible,intangible,direct and indirect costs? Give

Q55: A(n)_ is a document that describes how

Q56: Variances are calculated by subtracting the actual

Q57: A(n)_ might provide an estimate of $50

Q58: The main goal of the _ process

Q60: A large percentage of total project costs

Q62: The project management plan,project funding requirements,work performance

Q63: _ allow for future situations that are

Q64: _ allow for future situations that may

Q68:  The main outputs of the _ process

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines