The ____ is that portion of the approved total cost estimate planned to be spent on an activity during a given period.


A) AC
B) EV
C) RP
D) PV

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q84: The _ is the ratio of earned

Q85: _ and SPI less than one or

Q86: Many projects,particularly information technology projects,do not have

Q87: The WBS is not a required input

Q88: _ costs or benefits are costs or

Q90: In general,_ numbers for cost and schedule

Q91: _ is the earned value minus the

Q92: Project managers should focus on _,since they

Q93: Organizations have a history of spending too

Q94: There does not need to be a

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines