menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Computing
  3. Study Set
    Information Technology Project
  4. Exam
    Exam 7: Project Cost Management
  5. Question
    The ____ Is the Ratio of Earned Value to Planned
Solved

The ____ Is the Ratio of Earned Value to Planned

Question 84

Question 84

Multiple Choice

The ____ is the ratio of earned value to planned value and can be used to estimate the projected time to complete the project.


A) SV
B) CV
C) CPI
D) SPI

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q79: A _ is used to allocate money

Q80: Direct costs cannot be directly attributed to

Q81: _ are those costs that an organization

Q82: Any new technology or business process is

Q83: _ allows you to see a big-picture

Q85: _ and SPI less than one or

Q86: Many projects,particularly information technology projects,do not have

Q87: The WBS is not a required input

Q88: _ costs or benefits are costs or

Q89: The _ is that portion of the

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines