The ____ Provide(s)schedule-Related Information About Each Activity,such as Predecessors,successors,logical Relationships,leads
Multiple Choice
The ____ provide(s) schedule-related information about each activity,such as predecessors,successors,logical relationships,leads and lags,resource requirements,constraints,imposed dates,and assumptions related to the activity.
A) activity list
B) milestones
C) activity descriptions
D) activity attributes
Correct Answer:

Verified
Correct Answer:
Verified
Q53: _ have no duration and no resources
Q81: Activity information is not a required input
Q82: On a network diagram,all arrowheads should face
Q83: _ involves estimating how many people,equipment,and materials
Q84: There are _ main processes involved in
Q85: In the activity definition process,the project team
Q87: Many projects,especially in information technology,have very unrealistic
Q88: _ is a method of scheduling that
Q89: The activity list,activity attributes,activity resource requirements,resource calendars,project
Q90: What is a network diagram? What formats