Multiple Choice
____ is a method of scheduling that considers limited resources when creating a project schedule and includes buffers to protect the project completion date.
A) A Gantt chart
B) Critical path analysis
C) Critical chain scheduling
D) PERT analysis
Correct Answer:

Verified
Correct Answer:
Verified