Multiple Choice
____ involves monitoring identified and residual risks,identifying new risks,carrying out risk response plans,and evaluating the effectiveness of risk strategies throughout the life of the project.
A) Performing quantitative risk analysis
B) Planning risk responses
C) Monitoring and controlling risk
D) Performing qualitative risk analysis