Multiple Choice
A project manager can chart the probability and impact of risks on a ____.
A) risk ranking chart
B) risk probability table
C) probability/impact matrix
D) risk assessment matrix
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q26: _ involves doing whatever you can to
Q28: A(n) _ is a hierarchy of potential
Q28: Selecting the most experienced project manager is
Q30: Few organizations develop their own risk questionnaires.
Q35: The cost for risk management should not
Q36: _ involves monitoring identified and residual risks,identifying
Q39: _ involves reducing the impact of a
Q61: A probability/impact matrix or chart lists the
Q65: _ are indicators or symptoms of actual
Q75: _ risks are risks that remain after