Essay
Consider the following PERT/CPM network with estimated times in weeks.The project is scheduled to begin on May 1. The three-time estimate approach was used to calculate the expected times and the following table gives the variance for each activity:
a.Give the expected project completion date and the critical path.
b.By what date are you 99% sure the project will be completed?
Correct Answer:

Verified
a.16 weeks = Aug.21
...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q11: A critical activity can be part of
Q28: Arcs in a project network indicate<br>A)completion times.<br>B)precedence
Q31: For an activity with more than one
Q35: Slack equals<br>A)LF - EF.<br>B)EF - LF.<br>C)EF -
Q38: The difference between an activity's earliest finish
Q41: The project manager should monitor the progress
Q56: Mary Yetter,a staff analyst at the
Q59: Joseph King has ambitions to be mayor
Q63: A project has the following activities,precedence
Q66: Use the following network of related