A project has the following activities,precedence relationships,and time estimates in weeks:
a. Compute the expected time and variance for each activity.
b. Determine the critical path and the expected duration of the project.
c. What is the probability that the project will take longer than 56 weeks to complete?
Correct Answer:

Verified
a.
b.
c.SVt = 2.499...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q11: A critical activity can be part of
Q28: Arcs in a project network indicate<br>A)completion times.<br>B)precedence
Q31: For an activity with more than one
Q35: Slack equals<br>A)LF - EF.<br>B)EF - LF.<br>C)EF -
Q38: The difference between an activity's earliest finish
Q41: The project manager should monitor the progress
Q56: Mary Yetter,a staff analyst at the
Q59: Joseph King has ambitions to be mayor
Q61: Consider the following PERT/CPM network with
Q66: Use the following network of related