Solved

A Project Has the Following Activities,precedence Relationships,and Time Estimates in Weeks

Question 63

Essay

A project has the following activities,precedence relationships,and time estimates in weeks:  Activity  Immediate  Predecessor  Activities  Optimistic  Time (t0) Most Likely  Time (tm) Pessimistic  Time (tp) A 152025 B 81012 C  A 253040 D  B 151515 E  B 222527 F  E 152022 G  D 202022\begin{array} { c c c c c } \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor } \\\text { Activities }\end{array} & \begin{array} { c } \text { Optimistic } \\\text { Time } \left( t _ { 0 } \right)\end{array} & \begin{array} { c } \text { Most Likely } \\\text { Time } \left( t _ { \mathrm { m } } \right)\end{array} & \begin{array} { c } \text { Pessimistic } \\\text { Time } \left( t _ { \mathrm { p } } \right)\end{array} \\\hline \text { A } & - \cdot & 15 & 20 & 25 \\\text { B } & - & 8 & 10 & 12 \\\text { C } & \text { A } & 25 & 30 & 40 \\\text { D } & \text { B } & 15 & 15 & 15 \\\text { E } & \text { B } & 22 & 25 & 27 \\\text { F } & \text { E } & 15 & 20 & 22 \\\text { G } & \text { D } & 20 & 20 & 22 \\\hline \hline\end{array}
a. Compute the expected time and variance for each activity.
b. Determine the critical path and the expected duration of the project.
c. What is the probability that the project will take longer than 56 weeks to complete?

Correct Answer:

verifed

Verified

a. blured image b. blured image c.SVt = 2.499...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions