Multiple Choice
If the NPV (Net Present Value) of a project with one sign reversal is positive,then the project's IRR (Internal Rate of Return) ________ the required rate of return.
A) must be less than
B) must be greater than
C) could be greater or less than
D) cannot be determined without actual cash flows
Correct Answer:

Verified
Correct Answer: