Multiple Choice
In evaluating time-cost trade-offs, we start by crashing the task on the critical path that:
A) Has the lowest cost to reduce by one unit of time.
B) Has the lowest total crash cost.
C) Can be reduced the most.
D) Is the longest.
E) None of the these.
Correct Answer:

Verified
Correct Answer:
Verified