Solved

A Simple Sequential Project (Each Task Must Be Completed Before

Question 12

Multiple Choice

A simple sequential project (each task must be completed before the next one can begin) has the time estimates (in days) shown below: A simple sequential project (each task must be completed before the next one can begin)  has the time estimates (in days)  shown below:   What is the expected total time for the path? A) 7.33 days B) 9.00 days C) 10 days D) 12.67 days What is the expected total time for the path?


A) 7.33 days
B) 9.00 days
C) 10 days
D) 12.67 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions