If a Project Path Has an Expected Duration of 10

Question 11

Multiple Choice

If a project path has an expected duration of 10 days and a standard deviation of 3 days, what is the probability that the path will be completed in 10 days or less?


A) 0 percent
B) 33 percent
C) 50 percent
D) 75 percent

Correct Answer: