Task X has a most likely duration of 10 days,a best-case duration of 8 days,and a worst-case duration of 15 days.What is the probability that it will be completed in 12 days or less?
A) 0 percent
B) 95.7 percent
C) 90.1 percent
D) 75.3 percent