Colson Corp

Question 14

Multiple Choice

Colson Corp. has planned a simple project having four tasks. The task information for the project is shown below: Colson Corp. has planned a simple project having four tasks. The task information for the project is shown below:   What is the estimated completion time for the project? A) 29 days B) 25 days C) 22 days D) 19 days What is the estimated completion time for the project?


A) 29 days
B) 25 days
C) 22 days
D) 19 days