Multiple Choice
Colson Corp. has planned a simple project having four tasks. The task information for the project is shown below: What is the estimated completion time for the project?
A) 29 days
B) 25 days
C) 22 days
D) 19 days
Correct Answer:

Verified
Correct Answer:
Verified