Multiple Choice
Colson Corp. has planned a simple project having four tasks. The task information for the project is shown below: Does any task have slack? If so, how much?
A) None of the tasks have slack.
B) Task B has 3 days of slack.
C) Task C has 4 days of slack.
D) Task D has 2 days of slack.
E) Task C has 3 days of slack.
Correct Answer:

Verified
Correct Answer:
Verified