The network diagram below shows the five tasks required to complete a project and the associated times for those tasks. The network diagram below shows the five tasks required to complete a project and the associated times for those tasks.   Which of the following identifies the critical path tasks? A) A, B, D, F B) A, B, C, D, E, F C) A, B, E, F D) A, C, E, F Which of the following identifies the critical path tasks?


A) A, B, D, F
B) A, B, C, D, E, F
C) A, B, E, F
D) A, C, E, F