Rough-Cut Capacity Planning Does All of the Following EXCEPT

Question 28

Multiple Choice

Rough-cut capacity planning does all of the following EXCEPT:


A) Determines if a work center has the capacity to implement the MRP plan.
B) Uses planned order releases and scheduled receipts to estimate work center loads.
C) Develops a load profile.
D) Recalculates the MRP plan.

Correct Answer: