Multiple Choice
The following table shows capacity requirements data for making table tops. Which of the following is TRUE?
A) Overtime is needed in day 1.
B) Capacity exactly meets demand in day 5.
C) All of the excess demand in days 4 and 5 can be shifted to day 3.
D) New machines are needed.
Correct Answer:

Verified
Correct Answer:
Verified