Solved

The Network Below Represents a Project Being Analyzed by the Critical

Question 2

Essay

The network below represents a project being analyzed by the Critical Path Method. The network below represents a project being analyzed by the Critical Path Method.    a.What activity must be on the critical path, regardless of activity durations? b.What is the duration of path A-B-E-H-J? c.What is the critical path of this network? d.What is the length of the critical path?
a.What activity must be on the critical path, regardless of activity durations?
b.What is the duration of path A-B-E-H-J?
c.What is the critical path of this network?
d.What is the length of the critical path?

Correct Answer: