Which statement is true regarding activities not on the critical path?
A) Usually cannot be delayed
B) Have less slack than activities on the critical path
C) Can delay a project if they are highly variable
D) Are used to crash project completion times
Correct Answer:

Verified
Correct Answer:
Verified