Multiple Choice
When valuing a project using the Black-Scholes option pricing model,R is set equal to the:
A) historical real market rate of return.
B) annually compounded risk-free rate.
C) expected future real market rate of return.
D) continuously compounded risk-free rate.
E) project's CAPM rate of return.
Correct Answer: