Refer to the diagram below,where the numbers next to the arrows refer to the number of days required for completion of the corresponding activity.What is the critical path?
A) A-B-D-F
B) A-C-E-F
C) A-B-D-E-F
D) A-C-B-D-F
E) A-C-B-D-E-F