Solved

In Using an ABC System, All of the Following Steps

Question 120

Multiple Choice

In using an ABC system, all of the following steps are performed before the company's year begins except


A) identify the primary activities and estimate a total cost pool for each.
B) select an allocation base for each activity.
C) allocate the costs to the cost object using the activity cost allocation rates.
D) calculate an activity cost allocation rate for each activity.