Last Week Job # WPP 298 Was Charged: DM of $4,606;

Question 82

Multiple Choice

Last week Job # WPP 298 was charged: DM of $4,606; DL of $1,579; and, MOH of $3,960 based on machine hours.The materials requisition record for this week showed an additional purchase of 10 brackets at a unit cost of $16; the direct labour costs were the same as the first week; and, the total machine hours for both weeks are now 140 hours at $45 per machine hour.Calculate the revised total job cost.(direct materials + direct labour + manufacturing overhead) .


A) $10,145
B) $11,884
C) $12,645
D) $18,184
E) $14,224

Correct Answer:

verifed

Verified