Kenney Company uses activity-based costing to account for its manufacturing process. Kenney Company produces tires and each tire has $.50 of direct materials, includes 20 parts and requires 2 hours of machine time. There is no direct labor. Additional information follows: What is the cost of materials handling per tire?
A) $5.60
B) $16.00
C) $1.60
D) $3.20