Kenney Company Uses Activity-Based Costing to Account for Its Manufacturing

Question 77

Multiple Choice

Kenney Company uses activity-based costing to account for its manufacturing process. Kenney Company produces tires, and each tire has $.50 of direct materials, includes 20 parts and requires 2 hours of machine time. There is no direct labor. Additional information follows: Kenney Company uses activity-based costing to account for its manufacturing process. Kenney Company produces tires, and each tire has $.50 of direct materials, includes 20 parts and requires 2 hours of machine time. There is no direct labor. Additional information follows:   What is the cost of assembling per tire? A) $15.40 B) $7.00 C) $14.00 D) $28.00 What is the cost of assembling per tire?


A) $15.40
B) $7.00
C) $14.00
D) $28.00

Correct Answer:

verifed

Verified