Multiple Choice
What is the latest that activity B can start if A lasts 35 days, B lasts 5, days C lasts 6 days, and D lasts 7 days?
A) 35
B) 36
C) 40
D) 41
Correct Answer:

Verified
Correct Answer:
Verified