A Project Is Composed of the Twelve Activities Shown in the Table

Question 28

Essay

A project is composed of the twelve activities shown in the table. What are the earliest and latest start times for each of these activities?
 Activity  Time (days)  Predecessors  A 3 B 3 A  C 15 A  D 2 B  E 12 B  F 16 C  G 2 C  H 11 E, F  I 9 D, G  J 6 D, E  K 15 H, I  L 13 J, K \begin{array} { | c | c | c | } \hline \text { Activity } & \text { Time (days) } & \text { Predecessors } \\\hline \text { A } & 3 & \cdots \\\hline \text { B } & 3 & \text { A } \\\hline \text { C } & 15 & \text { A } \\\hline \text { D } & 2 & \text { B } \\\hline \text { E } & 12 & \text { B } \\\hline \text { F } & 16 & \text { C } \\\hline \text { G } & 2 & \text { C } \\\hline \text { H } & 11 & \text { E, F } \\\hline \text { I } & 9 & \text { D, G } \\\hline \text { J } & 6 & \text { D, E } \\\hline \text { K } & 15 & \text { H, I } \\\hline \text { L } & 13 & \text { J, K } \\\hline\end{array}

Correct Answer:

verifed

Verified

\[\begin{array} { | c | c | c | }
\hlin...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions